June 22-26
Monday: Trim for two remaining kitchen windows. Painters caulked, sanded and primed new trim. Continue reading Week 15: Skylight, paint, trim, skylight?
June 22-26
Monday: Trim for two remaining kitchen windows. Painters caulked, sanded and primed new trim. Continue reading Week 15: Skylight, paint, trim, skylight?
We moved into the house at the end of February 2000 and it has gone through many changes (I think improvements!) in the 15 years since. As I was looking at the new windows go in for the 2015 remodel, I started collecting the various “ages and stages” pictures for the back of the house and garden. Continue reading Evolution of the house since February 2000 – rear
June 15 – 19
Monday: The featured image is the skylights-to-be, in the hope that the roofer will be here on Friday to install the Velux skylights. The large one will be an opening solar skylight (like the others we installed last year to replace the fixed ones original to the house). The two narrow ones are fixed (cables in the rafters would be expensive to move, so this was a cost-effective compromise). Continue reading Week 14: sanding, texture, primer, caulk, paint
June 8-12
Monday: Windows delivered. Taper arrives mid morning -just one person, not a crew (he was sent on another job first). Continue reading Week 13: drywall taping, window installation
June 1-5
Monday: Sheetrock guys didn’t show until about 11:30am, then only brought in materials and papered the floors. Under two hours and they were off! Continue reading Week 12: drywall, skylight framing, taping?