Week 22: hardwood final coat, ramp sink, backsplash, glass template

August 10-14

Week 22 quick look

Monday: Backsplash for kitchen and downstairs half bath  & ramp sink for master bathroom.  A little nudge from the guy who runs Westhill apparently got the ramp sink to the head of the line. The slot drain is 1/8″ wider on one end, so they’ll have someone out tomorrow to do the Caesarstone equivalent of planing it to an even thickness. Continue reading Week 22: hardwood final coat, ramp sink, backsplash, glass template

Week 21: Carpet, network, painting, electrical

August 3-7

Week 21 Quick Look

Monday: Painters worked on bonus room, master bathroom, hall closet, pantry, back stair well and various touch ups. They also had to respray (after “floating” some filler to cover the chips) the family room cabinet doors. Continue reading Week 21: Carpet, network, painting, electrical