June 1-5
Monday: Sheetrock guys didn’t show until about 11:30am, then only brought in materials and papered the floors. Under two hours and they were off! Continue reading Week 12: drywall, skylight framing, taping?
June 1-5
Monday: Sheetrock guys didn’t show until about 11:30am, then only brought in materials and papered the floors. Under two hours and they were off! Continue reading Week 12: drywall, skylight framing, taping?
May 18 – 22
Monday: A noisy week begins – multiple rooms, multiple crews of people and very little quiet. Framing in master bathroom and electrical rough-in continues. Continue reading Week 10: framing, plumbing & electrical rough-in
April 20 – 24
Monday: Bathtub, faucets for vanity sinks and toilet installed. No water for the morning. Continue reading Week 6 – plumbing, garage drywall, glass?
March 23 – 27
Monday: drywall in the non-wet room parts of the bathroom. As we couldn’t have a medicine cabinet once we flipped the room back to its original orientation, I asked for a second niche, using lumber left over from the previous remodel (I’m a pack rat, but this time it did come in handy!) Continue reading Week 2 – drywall, drains & ducts
March 16 – 20
Monday: Very noisy day. Demolish the hall bathroom – nothing but studs and insulation left at the end of the day. Lots of drywall, two sinks and a cast iron tub headed out. Continue reading Week 1 – demolish the hall bathroom